King William Street, Tower Crane dismantle project
Posted on 18th June 2026 by Grace Goodall
0 minute read time
A busy weekend for our team at King William Street – 12D TM, supporting the final tower crane dismantle on a long-term project in the heart of the City of London.
The operation involved a 450t mobile crane, full road closure, 100m of Heras fencing, special signage, and close coordination with the fantastic team at City of London and TFL due to the sensitive location. Our TMOs, Danny, Will, Lee and Jack, were on site throughout the lifting operation, helping ensure the works were carried out safely and efficiently.
Great work from everyone involved in successfully delivering another project. Need Traffic Management? Call us on 01652 640996.